The overcurrent protection device is the main breaker. Some utilities may also require a fused AC disconnect between the inverter and the tap location. Line-side tap connection: This method requires that the wires from the inverter connect to the service wires on the line side of the circuit breaker. This connection is rarely allowed for.. With a line side tap, also called a supply side connection, the solar inverter is connected to a PV service fused disconnect and/or a solar only circuit breaker panel, which in turn is connected to a junction box. The junction box sits in between the main meter and the main service panel and houses the connections between the main breaker, the.
There are two basic approaches to connecting a grid-tied solar panel system, as shown in the wiring diagrams below. The most common is a "LOAD SIDE" connection, made AFTER the main breaker.. By connecting on the Line side, it avoids de-rating the existing service panel and avoids back-feed limits of the panel governed by Rules 1 and 2 above... This is the same as Standard Split-Phase installation, except that the inverter feeds directly into the power utility's grid. That is, the Solar CT is closer to the utility than the Grid CTs. This situation often arises when solar power is delivered via a line-side tap. Example Wiring Diagram Example Configuration Notes